Begin typing your search...

BHEL synchronises thermal power project

BHEL synchronises thermal power project
X

BHEL synchronises thermal power project

NEW DELHI: State-owned engineering firm Bharat Heavy Electricals on Wednesday announced synchronisation of 660-MW unit-2 of the 1,320-MW Maitree Super Thermal Power Project (STPP) with the electricity grid in Bangladesh. Synchronisation of a thermal power plant means beginning of electricity supply through main grid at prescribed parameters. The synchronisation of the unit has been done ahead of the commitment given at a high level G2G meeting, which was a very tough target even at the time it was given, a company statement said. Bharat Heavy Electricals Ltd (BHEL) has achieved a major milestone with the successful synchronisation of the 660-MW Unit-2 of the 1,320-MW Maitree Super Thermal Power Project (STPP) in Bangladesh, it stated.

Bizz Buzz
Next Story
Share it