479 infra projects show cost overruns worth Rs.4.4L cr
State-wise lockdown due to Covid-19 led to delay in implementation of these projects
image for illustrative purpose

As many as 479 infrastructure projects, each worth Rs 150 crore or more, have been hit by cost overruns totalling more than Rs 4.4 lakh crore, according to a report. The Ministry of Statistics and Programme Implementation monitors infrastructure projects worth Rs 150 crore and above. Of the 1,770 such projects, 479 reported cost overruns and 541 were delayed.
"Total original cost of implementation of the 1,770 projects was Rs 22,78,368.23 crore and their anticipated completion cost is likely to be Rs 27,19,218.09 crore, which reflects overall cost overruns of Rs 4,40,849.86 crore (19.35 per cent of original cost)," the ministry's latest report for June 2021 said.
According to the report, the expenditure incurred on these projects till June 2021 is Rs 13,22,374.82 crore, which is 48.63 per cent of the anticipated cost of the projects. However, the report said the number of delayed projects decreases to 396 if delay is calculated on the basis of latest schedule of completion.
Further, for 979 projects neither the year of commissioning nor the tentative gestation period has been reported. Out of 541 delayed projects, 109 projects have overall delay in the range of 1-12 months, 119 (13-24 months), 192 (25-26 months) and 121 projects (61 months and above). The average time overrun in these 541 delayed projects is 45.76 months.
Reasons for time overruns as reported by various project implementing agencies include delay in land acquisition, delay in obtaining forest and environment clearances, and lack of infrastructure support and linkages. Delay in tie-up for project financing, delay in finalisation of detailed engineering, change in scope, delay in tendering, ordering and equipment supply, and law and order problems, among others, are the other reasons, the report said.

